In April 2008, the OC Fair & Event Center Board of Directors approved
a three-year, $25 million capitol investment plan which is currently
in Phase I of the Master Plan approved in 2003. (Read
the full press release.)
This facility improvement plan includes: a 31,000-square-foot exhibit
hall with a aviation hanger design concept; renovation of the Main Mall;
creation of a breezeway between Buildings 14 and 16; relocation and construction
of a new Administration building; backstage improvements in Pacific Amphitheatre;
a commercial kitchen for food service; a corporation yard for storage
and facility upgrades; and an educational feature exhibit called Al’s
Brain, slated to premiere at 2009 OC Fair.
Periodically, updates will be posted here on the progress of these exciting
improvements at the OC Fair & Event Center. Please check back to
see how the fairgrounds are changing.
|
 |
|
Renderings
(Click on image to enlarge.) |
Watch how it happened
(Click on image to enlarge.) |
| |
 |
Rendering
(Click on image to enlarge.) |
Watch how it happened!
(Click on image to enlarge.) |
|
Hangar Building
The OC Fair & Event Center Technology Department is installing fiber optics and equipment for WiFi and an audio system within the new structure.
Green Gate
The pattern concrete walkway, which requires multiple set-ups and pours, is about 80 percent complete. An asphalt patch back around the tree islands and perimeter will be complete by Friday.
Miscellaneous: Crews are in the finishing stages of the Livestock Restrooms with plumbing and underground drainage near the parking lot side of the new facilities. The repairs for the underground utilities in the Main Mall are in the clean-up stages and the remaining trenches will be filled soon. Crews expect to break ground on the Gate 4 ½ project, which will upgrade the vehicle entrance gate to be more similar to Gates 5 and 8 off Arlington Drive. |
|
Hangar Building
Final touches for the new Hangar building are in the works with crews working on completion of the interior flooring and the asphalt surrounding the building. The 31,000-square-foot structure is the newest exhibit building at the OC Fair & Event Center offering an additional 23,000-square-foot exhibit space, meeting rooms, storage space and an exhibit show office under its 50-foot-tall arched ceiling.
Green Gate
OC Fair & Event Center crews have completed the underground utilities and are in the final phases of rough grading. Next, the contractor will resume the final grading and compacting before laying out and forming the patterned concrete surface.
Miscellaneous: With the drywall complete, OC Fair & Event Center crews are painting the interior wall surfaces of the new, permanent restrooms in the Livestock Area. Next, crews will install the stainless steel wainscoat paneling and porcelain floor. On the exterior, crews are installing block veneer and color coating the stucco finish. |

Hangar Building
(Click on photo to enlarge.)

Livestock Restrooms
(Click on photo to enlarge.)
|
|
 |